Work on District 300 Projects – Courier News

, ,

Written by Suzanne Baker. The Courier News. July 17, 2014.

http://couriernews.suntimes.com/2014/07/17/new-district-300-offices-taking-shape/

New District 300 Office Taking Shape

ALGONQUIN — While the rain in recent weeks set back school parking lot repairs in Community Unit School District 300, work on various projects throughout the district should be finished by the deadline, a school official is saying.

Assistant Superintendent of Operations Chuck Bumbales gave a brief update this week on the progress of the summer construction projects underway throughout the district.

The most noticeable change is at the site of the new administration center. What just weeks ago looked like a slab of concrete on vacant lot the corner of Golden Eagle and Harnish drives in Algonquin, now is starting to take shape as a building.

Bumbales said the steel was delivered and the basic frame for the structure took two days to erect. As of Monday, the roof was installed as welding crews moved onto the decking for the floors. He said the work should be completed by the end of the week so the concrete for the floor can be poured early next week.

Bumbales estimated the building will be fully enclosed within the next month and a half. He said after the concrete is poured on the second floor, the crew will move onto wrapping the steel around the building and then install the outer walls. The roofing would start after that, he said.

“Probably within a month and a half we should be water-tight in the building and then we should be moving quickly on the inside,” he said.

Work is projected to be completed around winter break.

With just weeks left before the Aug. 4 date to turn the building over to teachers, Bumbales said work on Oak Ridge School also continues to run on schedule.

He said work is continuing on the electrical, heating and air conditioning, sprinkler heads and system controls.

All the work in the ceiling passed inspection with the Regional Office of Education last week giving the green light for the construction crew to begin work on the drop ceiling, he said. With work on the tiling the floor already started, the next phase will be applying a final coat of paint and installing the doors and signage before cleaning up the facility.

With the start of the school year less than a month away, district officials expect air conditioning work and parking lot repairs to be done well before students arrive.

Bumbales said the air conditioning replacement at Dundee-Crown High School in Carpentersville, Sleepy Hollow Elementary in Sleepy Hollow, Neubert Elementary in Algonquin and Lake in the Hills Elementary in Lake in the Hills is on track to be finished before opening day of school Aug. 13.

While the district is on track to finish parking lot repairs before the start of the school year, Bumbales admitted a few locations will come down to the wire, particularly if the area is hit by frequent rain in the upcoming weeks. “We are on schedule, but it has been, well not even a little, a lot challenging,” Bumbales said.

The good news is that work is finished at Golfview Elementary, Lakewood Elementary, Perry Elementary and Dundee-Crown High School, all in Carpentersville; as well as Westfield School and Jacobs High School, both in Algonquin.

He said progress is being made at Parkview Elementary and the deLacy Family Education Center in Carpentersville; Lake in the Hills Elementary and Lincoln Prairie Elementary in Lake in the Hills; Sleep Hollow Elementary; Hampshire Elementary and Middle Schools in Hampshire; and Algonquin Lakes Elementary in Algonquin.

Construction is expected to start late this week to early next week on Neubert Elementary and Eastview Elementary in Algonquin; Dundee Highlands Elementary in West Dundee and Liberty Elementary in Carpentersville, according to Bumbales.