Library Projects In-Progress

Deerfield Library HVAC Replacement

Scope of Work: The project consists of various HVAC updates throughout the Deerfield Public Library, including removal and replacement of existing equipment and upgrades to instrumentation and controls.

Project Schedule: The project is scheduled to begin around February or March of 2027, after all materials have been procured. The project shall be completed within 6 months of starting.

The start date will be finalized with the awarded contractor after all submittals are approved and materials are ordered.

The building will remain occupied during construction, and a phasing plan will be established to minimize downtime and areas impacted during the project. The project will have a minimum of 8 Phases.

Fox River Valley Public Library – Dundee Library Improvements 

Will be complete by the end of October 2026; webpage coming soon!

This project includes exterior enhancements to the Dundee Library featuring new finishes, sunshades, roofing, aluminum windows, and HVAC equipment. The work also encompasses general trades improvements, including masonry, structural steel, carpentry, acoustic ceilings, exterior siding panels, painting, and associated mechanical and plumbing upgrades.

Ela Area Public Library

A webpage will be created once all phases are complete.

  • HVAC Updates:  This project includes comprehensive HVAC upgrades throughout the Ela Area Public Library to improve system performance and reliability. The scope includes removal and replacement of an existing chiller and air distribution equipment, along with upgrades to building instrumentation and controls (May 2026).
  • Interior Renovations: This project includes renovations at the Ela Area Public Library to improve functionality and user comfort. The scope features new flooring, acoustic enhancements, lighting replacement, and miscellaneous electrical improvements to modernize public spaces (Aug. – Dec. 2026).