Hawthorn SD 73 – Elementary School North Renovations – BR1

The project includes interior renovations (new floor, ceiling, and wall finishes) throughout an existing single story, 69,200 square foot elementary school. New interior drywall partitions, glazing systems, casework and furnishings will be installed throughout the building, along with complete mechanical system replacement, new and replaced plumbing fixtures, expanded fire protection system, and new lighting and electrical system upgrades.

This project will be completed in 4 Phases:

Phase 1 – 6/5/2023 – 10/31/2023
Phase 2 – 10/9/2023 – 1/26/2024
Phase 3 – 2/5/2024 – 5/31/2024
Phase 4 – 6/3/2024 – 8/1/2024

  • Owner

    Hawthorn District 73

  • Location

    301 West Hawthorn Parkway, Vernon Hills, IL

  • Project Dates

    In-Progress

  • Architect

    Legat Architects

  • Contact Us

    Get in touch with us today and allow our team of construction professionals to guide you on your next steps.